Originally posted by Chunder
View Post
In my 30+ years in this business I cannot tell you the number of times we have had to fight off the capability developers (the requirements people in the US) right up to to final production. And a simple add at a late stage can be ruinously expensive to a program in sustainment for years after deployment. Case in point....when the Army added a With Winch requirement to the HEMTT program at last minute it added costs associated to a) more tools to maintain the winch, b) cost for a new bumper and mounting bracket to handle the stress of the winch, c) training and certification to a truck driver to operate a winch, and d) increased annual servicing cots ($ & time) to test and certify every 6 months the winch cable.
Added tens of millions of dollars to life cycle costs.